| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/27/2009 | 8/27/2009 |
|
| WMR Request | 9/4/2009 | 3/30/2010 |
|
| GW Review Request | 9/4/2009 | 9/11/2009 |
|
| Transfer Initial Comment Period | 9/8/2009 | 9/8/2009 |
|
| Draft PD Issued | 6/24/2010 | 6/24/2010 |
|
| Field Peer Review | 8/3/2010 | 11/5/2010 |
|
| PD Issued | 8/6/2010 | 8/6/2010 |
|
| PD Weekly Public Notice | 8/10/2010 | 8/10/2010 |
|
| PD Issued | 9/10/2010 | 9/10/2010 |
|
| PD Weekly Public Notice | 9/14/2010 | 9/14/2010 |
|
| Final Order Issued | 11/5/2010 | 11/5/2010 |
|
| Certificate Remaining Issued | 11/5/2010 | |
RR Cert 86684 issued supercedes Cert 52623 -
RR Cert 86683 issued supercedes Cert 47618
|
| Certificate Remaining Issued | 4/5/2011 | |
RR Cert 86984 issued
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Received | 11/7/2022 | 11/7/2022 |
|
| Certificate Confirming Issued | 5/23/2025 | 5/23/2025 |
|