| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/12/2009 | 10/12/2009 |
|
| WMR Request | 10/15/2009 | 10/28/2009 |
|
| Transfer Initial Comment Period | 10/20/2009 | 10/20/2009 |
|
| Reimbursement Authority | 10/30/2009 | 4/9/2010 |
|
| RA Applicant Agreement | 11/17/2009 | 11/17/2009 |
|
| Draft PD Issued | 1/12/2010 | 1/12/2010 |
|
| PD Issued | 3/5/2010 | 3/5/2010 |
|
| PD Weekly Public Notice | 3/9/2010 | 3/9/2010 |
|
| Final Order Issued | 4/9/2010 | 4/9/2010 |
|
| Certificate Remaining Issued | 4/9/2010 | |
RR Cert 86185 issued supersedes Cert 29484
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| Extension Application Received | 10/5/2012 | 10/5/2012 |
|
| Extension FO Issued | 10/16/2012 | 10/16/2012 |
|
| Completion Due (C Date) | 10/17/2012 | 10/1/2013 |
|
| CBU Received | 1/8/2016 | 1/8/2016 |
|
| Certificate Confirming Issued | 5/9/2016 | 5/9/2016 |
|