| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/30/2009 | 11/30/2009 |
|
| WMR Request | 12/22/2009 | 12/23/2009 |
|
| ODFW Review | 12/22/2009 | 2/3/2010 |
|
| Reimbursement Authority | 12/29/2009 | 3/23/2010 |
|
| Transfer Initial Comment Period | 12/29/2009 | 12/29/2009 |
|
| RA Applicant Agreement | 1/1/2010 | 1/1/2010 |
|
| Deficiency Letter | 2/16/2010 | 2/24/2010 |
|
| Draft PD Issued | 3/1/2010 | 3/1/2010 |
|
| PD Issued | 3/23/2010 | 3/23/2010 |
|
| Consent to Injury Review Requested | 3/25/2010 | 3/25/2010 |
|
| PD Weekly Public Notice | 3/30/2010 | 3/30/2010 |
|
| ODFW Recommendation Notice | 5/25/2010 | 6/24/2010 |
|
| Final Order Issued | 7/12/2010 | 7/12/2010 |
|
| CBU Received | 1/4/2012 | 1/4/2012 |
|
| Certificate Confirming Issued | 5/1/2012 | 5/1/2012 |
|