Process Step | Date Initiated | Date Completed | Comments |
Received | 12/14/2009 | 12/14/2009 |
|
ODFW Review | 12/22/2009 | 12/29/2009 |
|
WMR Request | 12/22/2009 | 12/28/2009 |
|
Transfer Initial Comment Period | 12/29/2009 | 12/29/2009 |
|
Reimbursement Authority | 1/14/2010 | |
|
RA Applicant Agreement | 1/27/2010 | 1/27/2010 |
|
Deficiency Letter | 3/10/2010 | |
|
Draft PD Issued | 4/12/2010 | |
|
PD Issued | 5/7/2010 | 5/7/2010 |
|
PD Weekly Public Notice | 5/11/2010 | 5/11/2010 |
|
Final Order Issued | 6/29/2010 | 6/29/2010 |
|
Certificate Remaining Issued | 6/29/2010 | 6/29/2010 |
RR 86387 issued supesedes Certificate 81477
|
Extension FO Issued | 9/21/2011 | 9/21/2011 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
CBU Received | 11/26/2012 | 11/26/2012 |
|
Certificate Confirming Issued | 7/12/2013 | 7/12/2013 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|