| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/1/2010 | 2/1/2010 |
|
| Transfer Initial Comment Period | 2/9/2010 | 2/9/2010 |
|
| WMR Request | 2/9/2010 | 2/18/2010 |
|
| GW Review Request | 2/9/2010 | 3/2/2010 |
|
| Draft PD Issued | 3/13/2010 | |
|
| PD Issued | 4/13/2010 | 4/13/2010 |
|
| PD Weekly Public Notice | 4/20/2010 | 4/20/2010 |
|
| Final Order Issued | 6/23/2010 | 6/23/2010 |
|
| Final Order Issued | 8/8/2011 | 8/8/2011 |
|
| Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
| CBU Due | 10/1/2016 | 10/1/2016 |
|