| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/25/2010 | 2/25/2010 |
|
| Reimbursement Authority | 3/1/2010 | 7/22/2010 |
|
| WMR Request | 3/1/2010 | 3/5/2010 |
|
| GW Review Request | 3/1/2010 | 3/2/2010 |
|
| Transfer Initial Comment Period | 3/2/2010 | 3/2/2010 |
|
| RA Applicant Agreement | 4/15/2010 | 4/15/2010 |
|
| Draft PD Issued | 6/2/2010 | 6/2/2010 |
|
| PD Issued | 6/14/2010 | 6/14/2010 |
|
| PD Weekly Public Notice | 6/15/2010 | 6/15/2010 |
|
| Final Order Issued | 7/22/2010 | 7/22/2010 |
|
| Certificate Remaining Issued | 7/22/2010 | |
RR Cert 86445 issued supersedes Cert 82858
|
| CBU Received | 4/2/2013 | 4/2/2013 |
|
| Certificate Confirming Issued | 8/2/2013 | 8/2/2013 |
|
| Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
| CBU Due | 10/1/2016 | 10/1/2016 |
|