Process Step | Date Initiated | Date Completed | Comments |
Received | 2/26/2010 | 2/26/2010 |
|
Reimbursement Authority | 3/1/2010 | 6/7/2010 |
|
WMR Request | 3/1/2010 | 3/2/2010 |
|
GW Review Request | 3/1/2010 | 3/9/2010 |
|
Transfer Initial Comment Period | 3/2/2010 | 3/2/2010 |
|
Draft PD Issued | 4/2/2010 | 4/2/2010 |
|
PD Issued | 4/7/2010 | 4/7/2010 |
|
PD Weekly Public Notice | 4/13/2010 | 4/13/2010 |
|
Final Order Issued | 6/7/2010 | 6/7/2010 |
|
Certificate Remaining Issued | 6/7/2010 | |
RR Cert 86337 issued supersedes Cert 29097
|
CBU Received | 7/14/2011 | 7/14/2011 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
Certificate Confirming Issued | 1/23/2015 | 1/23/2015 |
|