Process Step | Date Initiated | Date Completed | Comments |
Received | 3/18/2010 | 3/18/2010 |
|
WMR Request | 3/29/2010 | 4/22/2010 |
|
Transfer Initial Comment Period | 3/30/2010 | 4/30/2010 |
|
ODFW Review | 6/4/2010 | 8/25/2010 |
|
Deficiency Letter | 3/13/2012 | 3/13/2012 |
|
Deficiency Letter | 5/7/2012 | 5/7/2012 |
|
Draft PD Issued | 4/3/2013 | 4/3/2013 |
|
PD Issued | 7/24/2013 | 7/24/2013 |
|
PD Weekly Public Notice | 8/6/2013 | 8/6/2013 |
|
Certificate Remaining Issued | 10/28/2013 | |
RR Cert 88903 issued supersedes Cert 39354; RR Cert 88904 issued supersedes Cert 39355; RR Cert 88905 issued supersedes Cert 39358; RR Cert 88906 issued supersedes Cert 86535
|
Final Order Issued | 10/28/2013 | 10/28/2013 |
|
CBU Due | 10/31/2013 | 10/1/2016 |
|
Completion Due (C Date) | 10/31/2013 | 10/1/2015 |
|
Extension Application Received | 1/3/2017 | 1/3/2017 |
|
Extension FO Issued | 1/23/2017 | 1/23/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Received | 9/30/2019 | 9/30/2019 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 11/19/2021 | 11/19/2021 |
|