| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/22/2010 | 3/22/2010 |
|
| WMR Request | 3/29/2010 | 4/23/2010 |
|
| Transfer Initial Comment Period | 3/30/2010 | 3/30/2010 |
|
| GW Review Request | 7/26/2010 | 10/6/2010 |
|
| Deficiency Letter | 10/13/2010 | 11/1/2010 |
|
| Draft PD Issued | 11/30/2010 | 11/30/2010 |
|
| PD Issued | 1/12/2011 | 1/12/2011 |
|
| PD Weekly Public Notice | 1/18/2011 | 1/18/2011 |
|
| Final Order Issued | 3/16/2011 | 3/16/2011 |
|
| Certificate Remaining Issued | 3/16/2011 | 3/16/2011 |
RR Cert 86890 and 86891
|
| CBU Received | 4/17/2012 | 4/17/2012 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Due | 10/1/2013 | 10/1/2013 |
|
| Certificate Confirming Issued | 4/24/2015 | 4/24/2015 |
|