| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/24/2010 | 5/24/2010 |
|
| GW Review Request | 5/28/2010 | 6/10/2010 |
|
| WMR Request | 5/28/2010 | 6/14/2010 |
|
| Transfer Initial Comment Period | 6/1/2010 | 6/1/2010 |
|
| Draft PD Issued | 7/28/2010 | 7/28/2010 |
|
| PD Issued | 8/31/2010 | 8/31/2010 |
|
| PD Weekly Public Notice | 9/7/2010 | 9/7/2010 |
|
| Final Order Issued | 10/8/2010 | 10/8/2010 |
|
| Certificate Remaining Issued | 10/8/2010 | |
RR Cert 86618 issued supercedes Cert 82605
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Due | 10/1/2013 | 10/1/2013 |
|
| CBU Received | 6/17/2016 | 6/17/2016 |
|
| CBU Received | 8/12/2019 | 8/12/2019 |
|
| Certificate Confirming Issued | 12/29/2023 | 12/29/2023 |
|