Process Step | Date Initiated | Date Completed | Comments |
Received | 5/26/2010 | 5/26/2010 |
|
WMR Request | 5/28/2010 | 6/23/2010 |
|
ODFW Review | 5/28/2010 | 6/23/2010 |
|
Transfer Initial Comment Period | 6/1/2010 | 6/1/2010 |
|
Draft PD Issued | 7/2/2010 | 7/2/2010 |
|
Field Peer Review | 8/26/2010 | 12/13/2010 |
|
PD Issued | 8/31/2010 | 8/31/2010 |
|
PD Weekly Public Notice | 9/7/2010 | 9/7/2010 |
|
Certificate Remaining Issued | 12/13/2010 | |
RR Cert 86743 issued supercedes Cert 3082
|
Final Order Issued | 12/13/2010 | 12/13/2010 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|