| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/27/2010 | 5/27/2010 |
|
| WMR Request | 5/28/2010 | 6/15/2010 |
|
| ODFW Review | 5/28/2010 | 8/25/2010 |
|
| Transfer Initial Comment Period | 6/1/2010 | 6/1/2010 |
|
| Draft PD Issued | 8/18/2010 | 8/18/2010 |
|
| Draft PD Issued | 10/25/2010 | 10/25/2010 |
|
| Field Peer Review | 11/2/2010 | 1/24/2011 |
|
| PD Issued | 11/9/2010 | 11/9/2010 |
|
| PD Weekly Public Notice | 11/16/2010 | 11/16/2010 |
|
| Final Order Issued | 1/24/2011 | 1/24/2011 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Received | 5/9/2013 | 5/9/2013 |
|
| CBU Due | 10/1/2013 | 10/1/2013 |
|
| Certificate Confirming Issued | 8/16/2016 | 8/16/2016 |
|