Process Step | Date Initiated | Date Completed | Comments |
Received | 7/7/2010 | 7/7/2010 |
|
WMR Request | 7/8/2010 | 7/12/2010 |
|
Transfer Initial Comment Period | 7/14/2010 | 7/14/2010 |
|
Reimbursement Authority | 4/20/2011 | |
|
RA Applicant Agreement | 6/3/2011 | 6/3/2011 |
|
Draft PD Issued | 7/21/2011 | 7/21/2011 |
|
PD Issued | 8/10/2011 | 8/10/2011 |
|
PD Weekly Public Notice | 8/16/2011 | 8/16/2011 |
|
Certificate Confirming Issued | 10/7/2011 | 10/7/2011 |
Certificate 87249 issued
|
Final Order Issued | 10/7/2011 | 10/7/2011 |
|