Process Step | Date Initiated | Date Completed | Comments |
Received | 8/12/2010 | 8/12/2010 |
|
WMR Request | 8/16/2010 | 9/2/2010 |
|
Transfer Initial Comment Period | 8/24/2010 | 9/24/2010 |
|
Draft PD Issued | 4/11/2012 | 4/11/2012 |
Contingent on approval of T-11121
|
News $ Due Letter | 5/24/2012 | 6/30/2012 |
|
PD Issued | 5/31/2012 | 5/31/2012 |
|
PD Weekly Public Notice | 7/31/2012 | 7/31/2012 |
|
Final Order Issued | 4/30/2013 | 4/30/2013 |
|
Certificate Confirming Issued | 4/30/2013 | 4/30/2013 |
CF Cert 88199, 88200, 88201 issued confirms the portion instream.
|
Certificate Remaining Issued | 4/30/2013 | 4/30/2013 |
RR Cert 88202 issued supersedes Cert 48992; RR Cert 88203 issued supersedes Cert 50112
|