Process Step | Date Initiated | Date Completed | Comments |
Received | 8/12/2010 | 8/12/2010 |
|
ODFW Review | 8/16/2010 | 8/30/2010 |
|
WMR Request | 8/16/2010 | 9/2/2010 |
|
Transfer Initial Comment Period | 8/24/2010 | 9/24/2010 |
|
Draft PD Issued | 4/11/2012 | 4/11/2012 |
Contingent on approval of T-11120 (instream transfer)
|
News $ Due Letter | 5/24/2012 | 5/31/2012 |
|
PD Issued | 5/31/2012 | 5/31/2012 |
|
Consent to Injury Review Requested | 5/31/2012 | 5/31/2012 |
|
PD Weekly Public Notice | 7/31/2012 | 7/31/2012 |
|
CTI Recommendation Comment Period | 3/12/2013 | 4/12/2013 |
|
Final Order Issued | 4/30/2013 | 4/30/2013 |
|
CBU Due | 5/3/2013 | 10/1/2015 |
|
Completion Due (C Date) | 5/3/2013 | 10/1/2014 |
|
CBU Received | 3/9/2020 | 3/9/2020 |
|
Certificate Confirming Issued | 7/12/2022 | 7/12/2022 |
|