| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/17/2010 | 11/17/2010 |
|
| WMR Request | 11/18/2010 | 11/19/2010 |
|
| GW Review Request | 11/18/2010 | 5/3/2011 |
|
| Transfer Initial Comment Period | 11/23/2010 | 11/23/2010 |
|
| Draft PD Issued | 6/9/2011 | 6/9/2011 |
|
| PD Issued | 6/13/2011 | 6/13/2011 |
|
| PD Weekly Public Notice | 6/21/2011 | 6/21/2011 |
|
| Final Order Issued | 7/21/2011 | 7/21/2011 |
|
| Completion Due (C Date) | 10/1/2014 | 10/1/2014 |
|
| CBU Received | 9/14/2015 | 9/14/2015 |
|
| CBU Due | 10/1/2015 | 10/1/2015 |
|
| Certificate Confirming Issued | 1/11/2019 | 1/11/2019 |
|
| Certificate Remaining Issued | 1/11/2019 | 1/11/2019 |
|