| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/24/2011 | 1/24/2011 |
|
| WMR Request | 1/28/2011 | 1/31/2011 |
|
| Transfer Initial Comment Period | 2/1/2011 | 2/1/2011 |
|
| Draft PD Issued | 8/19/2011 | 8/19/2011 |
|
| PD Issued | 9/7/2011 | 9/7/2011 |
|
| PD Weekly Public Notice | 9/13/2011 | 9/13/2011 |
|
| Certificate Remaining Issued | 10/18/2011 | 10/18/2011 |
RR Cert 87257 issued superceedes Cert 83602
|
| Final Order Issued | 10/18/2011 | 10/18/2011 |
|
| Completion Due (C Date) | 10/1/2013 | 10/1/2013 |
|
| CBU Due | 10/1/2014 | 10/1/2014 |
|
| CBU Received | 4/9/2015 | 4/9/2015 |
|
| Certificate Confirming Issued | 9/19/2017 | 9/19/2017 |
|