Process Step | Date Initiated | Date Completed | Comments |
Received | 3/7/2011 | 3/7/2011 |
|
WMR Request | 3/11/2011 | 3/14/2011 |
|
GW Review Request | 3/11/2011 | 5/10/2011 |
|
Transfer Initial Comment Period | 3/15/2011 | 3/15/2011 |
|
Draft PD Issued | 5/27/2011 | 5/27/2011 |
|
PD Issued | 6/14/2011 | 6/14/2011 |
|
PD Weekly Public Notice | 6/21/2011 | 6/21/2011 |
|
Final Order Issued | 9/20/2011 | 9/20/2011 |
|
Final Order Issued | 9/27/2011 | 9/27/2011 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|
Extension Application Received | 9/2/2014 | 9/2/2014 |
|
Extension FO Issued | 10/10/2014 | 10/10/2014 |
|
Completion Due (C Date) | 10/23/2014 | 10/1/2016 |
|
CBU Received | 10/28/2015 | 10/28/2015 |
|
CBU Due | 10/1/2016 | 10/1/2017 |
|
Certificate Confirming Issued | 7/12/2019 | 7/12/2019 |
|