Process Step | Date Initiated | Date Completed | Comments |
Received | 3/9/2011 | 3/9/2011 |
|
WMR Request | 3/11/2011 | 4/13/2011 |
|
Transfer Initial Comment Period | 3/15/2011 | 3/15/2011 |
|
Draft PD Issued | 4/15/2011 | 4/15/2011 |
|
PD Issued | 4/27/2011 | 4/27/2011 |
|
PD Weekly Public Notice | 5/3/2011 | 5/3/2011 |
|
Final Order Issued | 6/3/2011 | 6/3/2011 |
|
CBU Received | 10/12/2011 | 10/12/2011 |
|
Certificate Confirming Issued | 2/24/2012 | 2/24/2012 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|