Process Step | Date Initiated | Date Completed | Comments |
Received | 3/11/2011 | 3/11/2011 |
|
WMR Request | 3/17/2011 | 3/30/2011 |
|
Transfer Initial Comment Period | 3/22/2011 | 3/22/2011 |
|
Draft PD Issued | 4/29/2011 | 4/29/2011 |
|
PD Issued | 5/24/2011 | 5/24/2011 |
|
PD Weekly Public Notice | 5/31/2011 | 5/31/2011 |
|
Certificate Remaining Issued | 6/30/2011 | |
RR 87114 issued supercedes cert 31943
|
Final Order Issued | 6/30/2011 | 6/30/2011 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|
CBU Received | 8/27/2015 | 8/27/2015 |
|
Certificate Confirming Issued | 11/9/2018 | 11/9/2018 |
|