Process Step | Date Initiated | Date Completed | Comments |
Received | 3/23/2011 | 3/23/2011 |
|
WMR Request | 3/24/2011 | 4/27/2011 |
|
ODFW Review | 3/24/2011 | 6/13/2011 |
|
Transfer Initial Comment Period | 3/29/2011 | 3/29/2011 |
|
Draft PD Issued | 6/16/2011 | 6/16/2011 |
|
PD Issued | 7/27/2011 | 7/27/2011 |
|
PD Weekly Public Notice | 8/2/2011 | 8/2/2011 |
|
PD Weekly Public Notice | 8/30/2011 | 8/30/2011 |
|
PD Issued | 9/27/2011 | 9/27/2011 |
|
PD Weekly Public Notice | 10/4/2011 | 10/4/2011 |
|
Final Order Issued | 11/7/2011 | 11/7/2011 |
|
Certificate Remaining Issued | 11/7/2011 | |
RR 87281 issued supercedes Cert 85765
|
Certificate Remaining Issued | 11/7/2011 | |
RR 87279 issued supercedes Cert 49003
|
Certificate Remaining Issued | 11/7/2011 | |
RR 87280 issued supercedes Cert 85724
|
Final Order Issued | 6/1/2012 | 6/1/2012 |
|
Completion Due (C Date) | 10/1/2013 | 10/1/2013 |
|
Extension FO Issued | 4/2/2014 | 4/2/2014 |
|
Completion Due (C Date) | 4/10/2014 | 10/1/2015 |
|
CBU Due | 10/1/2014 | 10/1/2014 |
|
CBU Due | 10/1/2015 | 10/1/2016 |
|
CBU Received | 8/21/2019 | 8/21/2019 |
|
Certificate Confirming Issued | 1/21/2022 | 1/21/2022 |
|