| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/31/2011 | 3/31/2011 |
|
| WMR Request | 4/1/2011 | 4/27/2011 |
|
| Transfer Initial Comment Period | 4/5/2011 | 4/5/2011 |
|
| Draft PD Issued | 11/9/2011 | 11/9/2011 |
|
| PD Issued | 1/12/2012 | 1/12/2012 |
|
| PD Weekly Public Notice | 1/17/2012 | 1/17/2012 |
|
| Certificate Remaining Issued | 2/17/2012 | |
RR 87433 issued superseces Cert 65175
|
| Final Order Issued | 2/17/2012 | 2/17/2012 |
|
| CBU Received | 5/23/2012 | 5/23/2012 |
|
| Completion Due (C Date) | 10/1/2013 | 10/1/2013 |
|
| Certificate Confirming Issued | 12/20/2013 | 12/20/2013 |
|
| CBU Due | 10/1/2014 | 10/1/2014 |
|