Process Step | Date Initiated | Date Completed | Comments |
Received | 7/12/2011 | 7/12/2011 |
|
Reimbursement Authority | 7/12/2011 | |
|
WMR Request | 7/20/2011 | 8/19/2011 |
|
Transfer Initial Comment Period | 7/26/2011 | 7/26/2011 |
|
RA Applicant Agreement | 7/28/2011 | |
|
Draft PD Issued | 12/7/2011 | 12/7/2011 |
|
PD Issued | 3/13/2012 | 3/13/2012 |
|
PD Weekly Public Notice | 3/20/2012 | 3/20/2012 |
|
Certificate Confirming Issued | 5/22/2012 | 5/22/2012 |
CF CERT 87580 ISSUED SUPERSEDES CERT 46843; CF CERT 87581 ISSUED SUPERSEDES CERT 62741; CF CERT 87582 ISSUED SUPERSEDES CERT 62742; CF CERT 87583 ISSUED SUPERSEDES CERT 62743; CF CERT 87584 ISSUED SUPERSEDES CERT 63794; CF CERT 87585 ISSUED SUPERSEDES CERT 63795; CF CERT 87586 ISSUED SUPERSEDES CERT 63796;
|
Final Order Issued | 5/22/2012 | 5/22/2012 |
|