| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/29/2012 | 2/29/2012 |
|
| WMR Request | 3/1/2012 | 3/27/2012 |
|
| Transfer Initial Comment Period | 3/6/2012 | 4/5/2012 |
|
| Draft PD Issued | 3/8/2013 | 3/8/2013 |
|
| Administrative Hold | 3/19/2013 | 5/13/2013 |
|
| PD Issued | 5/17/2013 | 5/17/2013 |
|
| PD Weekly Public Notice | 5/28/2013 | 5/28/2013 |
|
| Final Order Issued | 6/26/2013 | 6/26/2013 |
|
| Certificate Remaining Issued | 6/26/2013 | 6/26/2013 |
|
| Completion Due (C Date) | 7/1/2013 | 10/1/2015 |
|
| CBU Due | 7/1/2013 | 10/1/2016 |
|
| Extension FO Issued | 8/4/2015 | 8/4/2015 |
|
| Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
| CBU Received | 12/23/2020 | 12/23/2020 |
|
| Certificate Confirming Issued | 6/4/2021 | 6/4/2021 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|