Process Step | Date Initiated | Date Completed | Comments |
Received | 3/19/2012 | 3/19/2012 |
|
WMR Request | 3/21/2012 | 4/19/2012 |
|
Transfer Initial Comment Period | 3/27/2012 | 4/26/2012 |
|
Deficiency Letter | 1/14/2013 | |
|
Draft PD Issued | 6/27/2013 | 6/27/2013 |
|
Draft PD Issued | 8/8/2013 | 8/8/2013 |
|
PD Issued | 8/26/2013 | 8/26/2013 |
|
PD Weekly Public Notice | 8/27/2013 | 8/27/2013 |
|
Protest Filed | 10/7/2013 | 9/17/2014 |
|
Certificate Remaining Issued | 9/18/2014 | |
RR Cert 89523 issued supersedes Cert 7641; RR Cert 89524 issued supersedes Cert 45299
|
Certificate Confirming Issued | 9/18/2014 | 9/18/2014 |
CF Cert 89515 and RR Cert 89516 supersedes Cert 10900; CF Cert 89517 and RR Cert 89518 supersedes Cert 10901; CF Cert 89519 and RR Cert 89520 supersedes Cert 42822; CF Cert 89521 and RR Cert 89522 supersedes Cert 8679
|
Final Order Issued | 9/18/2014 | 9/18/2014 |
|
Certificate Confirming Issued | 12/23/2016 | 12/23/2016 |
CERT 92204 ISSUED SUPERSEDES CERT 8679
|