Process Step | Date Initiated | Date Completed | Comments |
Received | 3/27/2012 | 3/27/2012 |
|
WMR Request | 3/28/2012 | 3/30/2012 |
|
GW Review Request | 3/28/2012 | 1/14/2013 |
|
Transfer Initial Comment Period | 4/3/2012 | 5/3/2012 |
|
Draft PD Issued | 4/11/2013 | 4/11/2013 |
|
News $ Due Letter | 4/26/2013 | 5/2/2013 |
|
PD Issued | 5/17/2013 | 5/17/2013 |
|
PD Weekly Public Notice | 5/28/2013 | 5/28/2013 |
|
Certificate Remaining Issued | 7/2/2013 | 7/2/2013 |
Cert 88564 issued supersedes Cert 83456
|
Final Order Issued | 7/2/2013 | 7/2/2013 |
|
CBU Due | 7/26/2013 | 10/1/2014 |
|
Completion Due (C Date) | 7/26/2013 | 10/1/2014 |
|
CBU Received | 11/28/2014 | 11/28/2014 |
|
Proposed Certificate Mailing | 9/9/2016 | 9/9/2016 |
|
Certificate Confirming Issued | 3/3/2017 | 3/3/2017 |
|
Final Order Issued | 8/6/2019 | 8/6/2019 |
|