Process Step | Date Initiated | Date Completed | Comments |
Received | 5/14/2012 | 5/14/2012 |
|
WMR Request | 5/21/2012 | 6/19/2012 |
|
GW Review Request | 5/21/2012 | 6/1/2012 |
|
Transfer Initial Comment Period | 5/22/2012 | 6/21/2012 |
|
Draft PD Issued | 11/20/2012 | 11/20/2012 |
|
News $ Due Letter | 1/3/2013 | |
|
PD Issued | 2/14/2013 | 2/14/2013 |
|
PD Weekly Public Notice | 2/19/2013 | 2/19/2013 |
|
Final Order Issued | 4/8/2013 | 4/8/2013 |
|
CBU Due | 4/12/2013 | 10/1/2015 |
|
Completion Due (C Date) | 4/12/2013 | 10/1/2014 |
|
CBU Received | 12/16/2019 | 12/16/2019 |
|
Certificate Confirming Issued | 4/8/2022 | 4/8/2022 |
|