Process Step | Date Initiated | Date Completed | Comments |
Received | 10/25/2012 | 10/25/2012 |
|
WMR Request | 10/29/2012 | 11/5/2012 |
|
Transfer Initial Comment Period | 10/30/2012 | 11/30/2012 |
|
Draft PD Issued | 11/28/2012 | 11/28/2012 |
|
PD Issued | 9/19/2013 | 9/19/2013 |
|
PD Weekly Public Notice | 9/24/2013 | 9/24/2013 |
|
Final Order Issued | 12/26/2013 | 12/26/2013 |
|
Certificate Remaining Issued | 12/26/2013 | 12/26/2013 |
RR Cert 88921 issued supersedes Cert 80372; RR Cert 88923 issued supersedes Cert 27737; RR Cert 88924 issued supersedes Cert 67383
|
Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
CBU Received | 9/9/2016 | 9/9/2016 |
|
CBU Due | 10/1/2016 | 10/1/2016 |
|
Certificate Confirming Issued | 10/15/2021 | 10/15/2021 |
|