Process Step | Date Initiated | Date Completed | Comments |
Received | 1/14/2013 | 1/14/2013 |
|
Transfer Initial Comment Period | 1/22/2013 | 2/22/2013 |
|
WMR Request | 1/22/2013 | 3/12/2013 |
|
GW Review Request | 1/22/2013 | 7/8/2013 |
|
Draft PD Issued | 11/26/2013 | 11/26/2013 |
|
News $ Due Letter | 1/23/2014 | 1/28/2014 |
|
PD Issued | 1/29/2014 | 1/29/2014 |
|
PD Weekly Public Notice | 2/4/2014 | 2/4/2014 |
|
Certificate Remaining Issued | 3/14/2014 | 3/14/2014 |
RR Cert 89133 issued supersedes Cert 55544
|
Final Order Issued | 3/14/2014 | 3/14/2014 |
|
Completion Due (C Date) | 3/14/2014 | 10/1/2016 |
|
CBU Due | 10/1/2016 | 10/1/2017 |
|
Extension Application Received | 5/16/2017 | |
|
Extension FO Issued | 5/18/2017 | 5/18/2017 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
CBU Completeness Review | 10/18/2022 | |
|
CBU Received | 10/18/2022 | 10/18/2022 |
|