Process Step | Date Initiated | Date Completed | Comments |
Received | 2/6/2013 | 2/6/2013 |
|
Transfer Initial Comment Period | 2/12/2013 | 3/15/2013 |
|
WMR Request | 2/12/2013 | 3/7/2013 |
|
Draft PD Issued | 3/8/2013 | 3/8/2013 |
|
PD Issued | 5/2/2013 | 5/2/2013 |
|
PD Weekly Public Notice | 5/14/2013 | 5/14/2013 |
|
Final Order Issued | 6/17/2013 | 6/17/2013 |
|
Completion Due (C Date) | 6/17/2013 | 10/1/2014 |
|
Certificate Remaining Issued | 6/17/2013 | 6/17/2013 |
RR Cert 88161 issued supersedes Cert 49211
|
CBU Due | 7/1/2013 | 10/1/2015 |
|
CBU Received | 12/31/2013 | 12/31/2013 |
|
Certificate Confirming Issued | 3/28/2014 | 3/28/2014 |
|