| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/13/2013 | 2/13/2013 |
|
| Transfer Initial Comment Period | 2/19/2013 | 3/22/2013 |
|
| WMR Request | 2/19/2013 | 3/4/2013 |
|
| ODFW Review | 2/19/2013 | 7/30/2013 |
|
| Draft PD Issued | 12/9/2013 | 12/9/2013 |
|
| PD Issued | 1/29/2014 | 1/29/2014 |
|
| PD Weekly Public Notice | 2/4/2014 | 2/4/2014 |
|
| Final Order Issued | 3/18/2014 | 3/18/2014 |
|
| Completion Due (C Date) | 3/18/2014 | 3/18/2014 |
|
| Certificate Remaining Issued | 3/18/2014 | 3/18/2014 |
RR Cert 89125 issued supersedes Cert 2458
|
| CBU Due | 10/1/2015 | 10/1/2015 |
|
| CBU Received | 6/23/2016 | 6/23/2016 |
|
| Certificate Confirming Issued | 10/15/2021 | 10/15/2021 |
|