Process Step | Date Initiated | Date Completed | Comments |
Received | 2/21/2013 | 2/21/2013 |
|
WMR Request | 2/28/2013 | 3/5/2013 |
|
Transfer Initial Comment Period | 3/5/2013 | 4/5/2013 |
|
Draft PD Issued | 6/18/2013 | 6/18/2013 |
|
PD Issued | 8/14/2013 | 8/14/2013 |
|
PD Weekly Public Notice | 9/3/2013 | 9/3/2013 |
|
Certificate Remaining Issued | 10/22/2013 | 10/22/2013 |
RR Cert 88900 issued supersedes Cert 87770
|
Final Order Issued | 10/22/2013 | 10/22/2013 |
|
CBU Due | 10/25/2013 | 10/1/2016 |
|
Completion Due (C Date) | 10/25/2013 | 10/1/2015 |
|