Process Step | Date Initiated | Date Completed | Comments |
Received | 3/26/2013 | 3/26/2013 |
|
WMR Request | 4/1/2013 | 4/23/2013 |
|
GW Review Request | 4/1/2013 | 11/6/2013 |
|
Transfer Initial Comment Period | 4/2/2013 | 5/3/2013 |
|
Draft PD Issued | 1/21/2014 | 2/14/2014 |
|
PD Issued | 4/2/2014 | 4/2/2014 |
|
PD Weekly Public Notice | 4/15/2014 | 4/15/2014 |
|
Final Order Issued | 5/29/2014 | 5/29/2014 |
|
Completion Due (C Date) | 5/29/2014 | 10/1/2015 |
|
CBU Received | 11/14/2014 | 11/14/2014 |
|
Certificate Confirming Issued | 5/1/2015 | 5/1/2015 |
|
CBU Due | 10/1/2015 | 10/1/2016 |
|