Process Step | Date Initiated | Date Completed | Comments |
Received | 4/24/2013 | 4/24/2013 |
|
Transfer Initial Comment Period | 4/30/2013 | 5/31/2013 |
|
GW Review Request | 4/30/2013 | 5/14/2013 |
|
WMR Request | 4/30/2013 | 8/18/2014 |
|
Deficiency Letter | 6/10/2013 | 6/10/2013 |
|
Deficiency Letter | 7/18/2013 | 7/18/2013 |
|
Deficiency Letter | 8/9/2013 | 8/9/2013 |
|
Deficiency Letter | 9/18/2013 | 9/18/2014 |
|
Deficiency Letter | 10/15/2013 | 10/15/2013 |
|
Deficiency Letter | 10/23/2013 | 10/23/2013 |
|
ODFW Review | 12/18/2013 | 12/26/2013 |
|
WMR Request | 12/18/2013 | 8/18/2014 |
|
Transfer Initial Comment Period | 12/24/2013 | 1/24/2014 |
|
Deficiency Letter | 3/31/2014 | 3/31/2014 |
|
Draft PD Issued | 6/4/2014 | 6/4/2014 |
|
PD Issued | 9/8/2014 | 9/8/2014 |
|
PD Weekly Public Notice | 9/16/2014 | 9/16/2014 |
|
Final Order Issued | 10/24/2014 | 10/24/2014 |
|
Completion Due (C Date) | 10/24/2014 | 10/1/2016 |
|
Final Order Issued | 11/24/2015 | 11/24/2015 |
|
CBU Due | 10/1/2016 | 10/1/2017 |
|
CBU Received | 8/15/2018 | 8/15/2018 |
|
Certificate Confirming Issued | 12/29/2023 | 12/29/2023 |
|