| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/26/2013 | 4/26/2013 |
|
| Reimbursement Authority | 5/1/2013 | 5/17/2013 |
|
| WMR Request | 5/1/2013 | 5/2/2013 |
|
| GW Review Request | 5/1/2013 | 5/15/2013 |
|
| Transfer Initial Comment Period | 5/7/2013 | 6/7/2013 |
|
| Draft PD Issued | 1/8/2014 | 1/8/2014 |
|
| News $ Due Letter | 2/20/2014 | 2/20/2014 |
|
| PD Issued | 2/28/2014 | 2/28/2014 |
|
| PD Weekly Public Notice | 3/4/2014 | 3/4/2014 |
|
| Final Order Issued | 4/15/2014 | 4/15/2014 |
|
| Completion Due (C Date) | 4/15/2014 | 4/15/2014 |
|
| CBU Due | 10/1/2016 | 10/1/2016 |
|
| CBU Received | 10/12/2016 | 10/12/2016 |
|
| Certificate Confirming Issued | 3/27/2017 | 3/27/2017 |
|