Process Step | Date Initiated | Date Completed | Comments |
Received | 5/28/2013 | 5/28/2013 |
|
Transfer Initial Comment Period | 6/4/2013 | 7/5/2013 |
|
WMR Request | 6/4/2013 | 7/30/2013 |
|
Draft PD Issued | 2/13/2014 | 2/13/2014 |
|
PD Issued | 3/24/2014 | 3/24/2014 |
|
PD Weekly Public Notice | 4/1/2014 | 4/1/2014 |
|
Final Order Issued | 5/1/2014 | 5/1/2014 |
|
Completion Due (C Date) | 5/1/2014 | 10/1/2015 |
|
Certificate Remaining Issued | 5/1/2014 | 5/1/2014 |
RR CERT 89239 issued supersedes CERT 22179
|
CBU Due | 10/1/2015 | 10/1/2016 |
|
CBU Received | 11/10/2016 | 11/10/2016 |
|
Certificate Confirming Issued | 10/15/2021 | 10/15/2021 |
|