| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/28/2013 | 6/28/2013 |
|
| Transfer Initial Comment Period | 7/2/2013 | 8/2/2013 |
|
| WMR Request | 7/2/2013 | 7/2/2013 |
|
| ODFW Review | 7/2/2013 | 7/19/2013 |
|
| Draft PD Issued | 2/17/2015 | 2/17/2015 |
|
| PD Issued | 3/20/2015 | 3/20/2015 |
|
| PD Weekly Public Notice | 3/24/2015 | 3/24/2015 |
|
| Final Order Issued | 5/4/2015 | 5/4/2015 |
|
| Certificate Remaining Issued | 5/4/2015 | 5/4/2015 |
90143 issued supersedes 20977
|
| Certificate Remaining Issued | 9/4/2015 | 9/4/2015 |
90754 issued supersedes 20977
|
| Final Order Issued | 9/4/2015 | 9/4/2015 |
reconsidered
|
| Final Order Issued | 9/15/2015 | 9/15/2015 |
|
| CBU Received | 9/25/2015 | 9/25/2015 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
| CBU Due | 10/1/2017 | 10/1/2017 |
|
| Certificate Confirming Issued | 3/25/2022 | 3/25/2022 |
|