| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/10/2013 | 7/10/2013 |
|
| Transfer Initial Comment Period | 7/16/2013 | 8/16/2013 |
|
| WMR Request | 7/16/2013 | 8/15/2013 |
|
| ODFW Review | 7/16/2013 | 8/19/2013 |
|
| Reimbursement Authority | 7/22/2013 | 10/21/2013 |
|
| Draft PD Issued | 9/5/2013 | 9/5/2013 |
|
| PD Issued | 9/11/2013 | 9/11/2013 |
|
| PD Weekly Public Notice | 9/17/2013 | 9/17/2013 |
|
| Final Order Issued | 10/21/2013 | 10/21/2013 |
|
| CBU Due | 10/21/2013 | 10/21/2013 |
|
| Completion Due (C Date) | 10/21/2013 | 10/21/2013 |
|
| CBU Completeness Review | 11/30/2021 | 12/8/2021 |
|
| CBU Received | 11/30/2021 | 11/30/2021 |
|
| Final Order Issued | 12/29/2021 | 12/29/2021 |
|