| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/6/2013 | 8/6/2013 |
|
| Transfer Initial Comment Period | 8/6/2013 | 9/6/2013 |
|
| WMR Request | 8/6/2013 | 9/9/2013 |
|
| Draft PD Issued | 12/18/2013 | 12/18/2013 |
|
| PD Issued | 12/26/2013 | 12/26/2013 |
|
| PD Weekly Public Notice | 12/31/2013 | 12/31/2013 |
|
| Final Order Issued | 2/14/2014 | 2/14/2014 |
|
| Completion Due (C Date) | 2/14/2014 | 10/1/2015 |
|
| Certificate Remaining Issued | 2/14/2014 | 2/14/2014 |
RR Cert 89077 issued supersedes Cert 54059
|
| CBU Due | 10/1/2015 | 10/1/2015 |
|
| CBU Received | 4/5/2023 | 4/5/2023 |
|
| Certificate Confirming Issued | 5/23/2025 | 5/23/2025 |
|