Process Step | Date Initiated | Date Completed | Comments |
Reimbursement Authority | 8/2/2013 | 12/23/2013 |
|
Received | 8/9/2013 | 8/9/2013 |
|
WMR Request | 8/19/2013 | 9/10/2013 |
|
ODFW Review | 8/19/2013 | 10/9/2013 |
|
Transfer Initial Comment Period | 8/20/2013 | 9/20/2013 |
|
PD Issued | 7/25/2014 | 7/25/2014 |
|
PD Weekly Public Notice | 7/29/2014 | 7/29/2014 |
|
Final Order Issued | 2/9/2015 | 2/9/2015 |
|
Extension Application Received | 4/18/2016 | 4/18/2016 |
|
Extension FO Issued | 5/21/2016 | 5/21/2016 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
CBU Due | 10/1/2017 | 10/1/2017 |
|
CBU Due | 10/1/2017 | 10/1/2017 |
|
Final Order Issued | 8/9/2018 | 8/9/2018 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Received | 11/23/2018 | 11/23/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|