| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/15/2013 | 8/15/2013 |
|
| WMR Request | 8/19/2013 | 9/26/2013 |
|
| Transfer Initial Comment Period | 8/20/2013 | 9/20/2013 |
|
| GW Review Request | 8/27/2013 | 11/21/2013 |
|
| Draft PD Issued | 3/17/2014 | 3/17/2014 |
|
| PD Issued | 4/18/2014 | 4/18/2014 |
|
| PD Weekly Public Notice | 4/22/2014 | 4/22/2014 |
|
| Final Order Issued | 6/3/2014 | 6/3/2014 |
|
| Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
| CBU Received | 1/7/2016 | 1/7/2016 |
|
| CBU Due | 10/1/2016 | 10/1/2016 |
|
| Proposed Certificate Mailing | 3/10/2023 | 3/10/2023 |
|
| Certificate Confirming Issued | 7/7/2023 | 7/7/2023 |
|