Process Step | Date Initiated | Date Completed | Comments |
Received | 9/5/2013 | 9/5/2013 |
|
WMR Request | 9/16/2013 | 9/17/2013 |
|
ODFW Review | 9/16/2013 | 11/18/2013 |
|
Transfer Initial Comment Period | 9/17/2013 | 10/18/2013 |
|
Draft PD Issued | 5/12/2014 | 5/16/2014 |
|
News $ Due Letter | 6/4/2014 | 6/16/2014 |
|
PD Issued | 6/18/2014 | 6/18/2014 |
|
PD Weekly Public Notice | 6/24/2014 | 6/24/2014 |
|
Final Order Issued | 8/20/2014 | 8/20/2014 |
|
Certificate Remaining Issued | 8/20/2014 | 8/20/2014 |
RR Cert 89362 issued supersedes Cert 6424
|
CBU Due | 10/1/2015 | 10/1/2016 |
|
Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
CBU Received | 8/30/2016 | 8/30/2016 |
|
Certificate Confirming Issued | 4/28/2023 | 4/28/2023 |
|