Process Step | Date Initiated | Date Completed | Comments |
Received | 10/7/2013 | 10/7/2013 |
|
WMR Request | 10/15/2013 | 10/30/2013 |
|
GW Review Request | 10/15/2013 | 11/6/2013 |
|
Transfer Initial Comment Period | 10/22/2013 | 11/22/2013 |
|
Draft PD Issued | 2/14/2014 | 2/14/2014 |
|
PD Issued | 6/4/2014 | 6/4/2014 |
|
PD Weekly Public Notice | 6/10/2014 | 6/10/2014 |
|
Final Order Issued | 7/31/2014 | 7/31/2014 |
|
Completion Due (C Date) | 7/31/2014 | 7/31/2014 |
|
Certificate Remaining Issued | 7/31/2014 | 7/31/2014 |
RR Cert 89368 issued supersedes Cert 72361
|
CBU Due | 10/1/2015 | 10/1/2016 |
|
CBU Received | 1/11/2016 | 1/11/2016 |
|
Certificate Confirming Issued | 3/26/2021 | 3/26/2021 |
|