| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/18/2013 | 12/18/2013 |
|
| WMR Request | 12/26/2013 | 1/6/2014 |
|
| GW Review Request | 12/26/2013 | 12/31/2013 |
|
| Transfer Initial Comment Period | 12/31/2013 | 1/31/2014 |
|
| Draft PD Issued | 8/1/2014 | 8/1/2014 |
|
| PD Issued | 10/23/2014 | 10/23/2014 |
|
| PD Weekly Public Notice | 10/28/2014 | 10/28/2014 |
|
| Final Order Issued | 12/10/2014 | 12/10/2014 |
|
| Completion Due (C Date) | 12/10/2014 | 10/1/2016 |
|
| CBU Due | 10/1/2016 | 10/1/2017 |
|
| CBU Received | 11/28/2016 | 11/28/2016 |
|
| Certificate Confirming Issued | 4/19/2017 | 4/19/2017 |
|