| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/17/2014 | 1/17/2014 |
|
| WMR Request | 1/29/2014 | 2/10/2014 |
|
| ODFW Review | 1/29/2014 | 2/21/2014 |
|
| Transfer Initial Comment Period | 2/4/2014 | 3/7/2014 |
|
| Draft PD Issued | 10/9/2014 | 11/10/2014 |
|
| News $ Due Letter | 11/26/2014 | 12/26/2014 |
|
| PD Issued | 1/6/2015 | 1/6/2015 |
|
| PD Weekly Public Notice | 1/13/2015 | 1/13/2015 |
|
| Final Order Issued | 2/27/2015 | 2/27/2015 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
| CBU Due | 10/1/2017 | 10/1/2017 |
|
| Extension Application Received | 12/20/2017 | |
|
| Extension FO Issued | 1/19/2018 | 1/19/2018 |
|
| CBU Received | 4/30/2018 | 4/30/2018 |
|
| Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
| CBU Due | 10/1/2020 | 10/1/2020 |
|
| Certificate Confirming Issued | 6/25/2021 | 6/25/2021 |
|