| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/17/2014 | 3/17/2014 |
|
| WMR Request | 3/24/2014 | 8/19/2014 |
|
| ODFW Review | 3/24/2014 | 5/21/2014 |
|
| Transfer Initial Comment Period | 3/25/2014 | 4/25/2014 |
|
| Draft PD Issued | 11/24/2014 | 1/28/2015 |
|
| News $ Due Letter | 2/6/2015 | 2/12/2015 |
|
| PD Issued | 2/19/2015 | 2/19/2015 |
|
| PD Weekly Public Notice | 2/24/2015 | 2/24/2015 |
|
| Certificate Remaining Issued | 4/6/2015 | 4/6/2015 |
90162 issued supersedes 2334
|
| Final Order Issued | 12/24/2015 | 12/24/2015 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
| CBU Received | 9/21/2017 | 9/21/2017 |
|
| CBU Due | 10/1/2017 | 10/1/2017 |
|
| Certificate Confirming Issued | 7/16/2021 | 7/16/2021 |
|