Process Step | Date Initiated | Date Completed | Comments |
Draft PD Issued | 6/11/2013 | 6/11/2013 |
|
Received | 3/19/2014 | 3/19/2014 |
|
WMR Request | 3/24/2014 | 3/26/2014 |
|
GW Review Request | 3/24/2014 | 6/4/2014 |
|
Transfer Initial Comment Period | 3/25/2014 | 4/25/2014 |
|
Reimbursement Authority | 4/7/2014 | 8/20/2014 |
|
RA Applicant Agreement | 5/12/2014 | 5/12/2014 |
|
PD Issued | 7/10/2014 | 7/10/2014 |
|
PD Weekly Public Notice | 7/15/2014 | 7/15/2014 |
|
Final Order Issued | 8/20/2014 | 8/20/2014 |
|
CBU Due | 10/1/2015 | 10/1/2015 |
|
Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
CBU Received | 12/10/2015 | 12/10/2015 |
|
Certificate Confirming Issued | 9/27/2019 | 9/27/2019 |
|