| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/26/2014 | 3/26/2014 |
|
| WMR Request | 4/4/2014 | 8/5/2014 |
|
| GW Review Request | 4/4/2014 | 4/9/2014 |
|
| Transfer Initial Comment Period | 4/8/2014 | 5/9/2014 |
|
| Deficiency Letter | 9/4/2014 | 9/4/2014 |
|
| Draft PD Issued | 10/17/2014 | 10/17/2014 |
|
| PD Issued | 11/13/2014 | 11/13/2014 |
|
| PD Weekly Public Notice | 11/18/2014 | 11/18/2014 |
|
| Completion Due (C Date) | 12/18/2014 | 10/1/2016 |
|
| Final Order Issued | 12/18/2014 | 12/18/2014 |
|
| CBU Received | 7/29/2016 | 7/29/2016 |
|
| CBU Due | 10/1/2016 | 10/1/2017 |
|
| Certificate Confirming Issued | 1/9/2017 | 1/9/2017 |
|