| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/11/2014 | 4/11/2014 |
|
| WMR Request | 4/21/2014 | 6/12/2014 |
|
| ODFW Review | 4/21/2014 | 6/13/2014 |
|
| Transfer Initial Comment Period | 4/22/2014 | 5/23/2014 |
|
| Draft PD Issued | 9/26/2014 | 9/26/2014 |
|
| PD Issued | 11/25/2014 | 11/25/2014 |
|
| PD Weekly Public Notice | 12/9/2014 | 12/9/2014 |
|
| Final Order Issued | 1/22/2015 | 1/22/2015 |
|
| Completion Due (C Date) | 1/22/2015 | 10/1/2016 |
|
| Certificate Remaining Issued | 1/22/2015 | 1/22/2015 |
RR Cert 89762 issued supersedes Cert 47497; RR Cert 89763 issued supersedes Cert 9633
|
| CBU Due | 10/1/2016 | 10/1/2017 |
|
| CBU Received | 9/29/2017 | 9/29/2017 |
|
| Certificate Confirming Issued | 4/28/2023 | 4/28/2023 |
|