Process Step | Date Initiated | Date Completed | Comments |
Received | 5/9/2014 | 5/9/2014 |
|
WMR Request | 5/19/2014 | 7/2/2014 |
|
GW Review Request | 5/19/2014 | 8/14/2014 |
|
Transfer Initial Comment Period | 5/20/2014 | 6/20/2014 |
|
Reimbursement Authority | 6/16/2014 | 12/18/2014 |
|
RA Applicant Agreement | 6/25/2014 | 6/25/2014 |
|
Draft PD Issued | 9/8/2014 | 9/8/2014 |
|
News $ Due Letter | 10/7/2014 | 10/17/2014 |
|
PD Issued | 10/20/2014 | 10/20/2014 |
|
PD Weekly Public Notice | 10/28/2014 | 10/28/2014 |
|
Final Order Issued | 12/18/2014 | 12/18/2014 |
|
Certificate Remaining Issued | 12/18/2014 | 12/18/2014 |
RR Cert 89753 issued supersedes Cert 85895; RR Cert 89754 issued supersedes Cert 54875
|
Completion Due (C Date) | 12/23/2014 | 10/1/2016 |
|
CBU Due | 10/1/2016 | 10/1/2017 |
|
CBU Received | 10/24/2016 | 10/24/2016 |
|
Certificate Confirming Issued | 3/30/2017 | 3/30/2017 |
|